Realtime National Passenger Train Stats
Tuesday, 20 October 2026
Connection status: Connecting…
Follow the site's progress
Leave your email to hear about new features as they land.
Occasional development updates only — your address is never shared.
Last updated: 22:31:56
On Time
17060
82.7%
Late
3561
17.3%
Cancelled / Very Late
861
4.2%
Total
20621
National PPM
82%
Rolling: 84%
Counts are for today so far — every train is counted once, on arrival at its final destination.
Best Performing Operator
Merseyrail
On Time
98.4%
Late
1.6%
Cancelled / Very Late
0.4%
Total Trains
569
PPM: 98%
Worst Performing Operator
Avanti West Coast
On Time
50.5%
Late
49.5%
Cancelled / Very Late
9.5%
Total Trains
283
PPM: 50%
Passenger Operators
| Operator | On Time | Late | Cxl / V. Late | Total | PPM | Rolling |
|---|---|---|---|---|---|---|
| Avanti West Coast | 143 | 140 | 27 | 283 | 50% | 54% |
| c2c | 275 | 60 | 18 | 335 | 82% | 67% |
| Caledonian Sleeper Limited | 2 | 1 | 0 | 3 | 66% | — |
| Chiltern | 289 | 31 | 2 | 320 | 90% | 96% |
| CrossCountry | 189 | 55 | 18 | 244 | 77% | 86% |
| East Midlands Railway | 384 | 71 | 8 | 455 | 84% | 76% |
| Elizabeth line | 779 | 182 | 72 | 961 | 81% | 100% |
| Grand Central | 15 | 3 | 0 | 18 | 83% | 0% |
| Great Western Railway | 1176 | 366 | 156 | 1542 | 76% | 85% |
| Greater Anglia | 1117 | 60 | 1 | 1177 | 94% | 93% |
| Greater Thameslink Railway | 2455 | 611 | 129 | 3066 | 80% | 80% |
| Heathrow Express | 100 | 40 | 10 | 140 | 71% | 100% |
| Hull Trains | 13 | 1 | 0 | 14 | 92% | 50% |
| London North Eastern Railway | 149 | 26 | 3 | 175 | 85% | 75% |
| London Overground | 1304 | 128 | 37 | 1432 | 91% | 83% |
| Lumo East Coast | 8 | 2 | 0 | 10 | 80% | 100% |
| Lumo West Coast | 6 | 1 | 0 | 7 | 85% | 50% |
| Merseyrail | 560 | 9 | 2 | 569 | 98% | 100% |
| Northern Trains | 2044 | 461 | 71 | 2505 | 81% | 84% |
| ScotRail | 1691 | 332 | 64 | 2023 | 83% | 89% |
| South Western Railway | 1159 | 338 | 87 | 1497 | 77% | 84% |
| Southeastern | 1374 | 245 | 17 | 1619 | 84% | 82% |
| TransPennine Trains | 223 | 54 | 19 | 277 | 80% | 78% |
| Transport for Wales | 753 | 210 | 98 | 963 | 78% | 75% |
| West Midlands Trains | 994 | 181 | 32 | 1175 | 84% | 85% |
Freight Operators
Freight PPM counts trains arriving within 15 minutes of schedule.
| Operator | On Time | Late | Cxl / V. Late | Total | PPM | Rolling |
|---|---|---|---|---|---|---|
| Colas Freight | 20 | 1 | 1 | 21 | 95% | — |
| DB Cargo | 92 | 9 | 0 | 101 | 91% | 80% |
| Direct Rail Services | 25 | 2 | 0 | 27 | 92% | 50% |
| Freightliner Intermodal | 41 | 7 | 0 | 48 | 85% | 80% |
| GB Railfreight | 92 | 10 | 1 | 102 | 90% | 93% |
| Heavy Haul Rail | 69 | 8 | 0 | 77 | 89% | 100% |
| Network Rail - Materials | 62 | 8 | 0 | 70 | 88% | — |
How is performance measured?
The Public Performance Measure (PPM) is Network Rail's own headline figure: the percentage of trains arriving at their final destination within 5 minutes of schedule (10 minutes for long-distance, 15 for freight). "Rolling" is the PPM for the most recent hour. Figures show — until an operator has run trains today, and colours follow Network Rail's red/amber/green thresholds.
Note: Passenger operators must have at least 10 trains in service today to be included in the best/worst ranking; freight operators are not ranked.
Data received from Network Rail every minute. Railway day runs from 02:00 to 01:59 the next day.
Note: Data is approximate and may not be 100% accurate.